Introduction

An elevation drawing is a flat view of a building or structure seen from the side, with heights shown to scale. A plan looks down from above and shows length and width, and an elevation shows height. It is where an estimator finds how tall a wall is, how high a pipe runs or how far above the floor a device sits.

Estimators use elevations by hand, flipping between the plan sheet and the elevation sheet. They write the heights onto the plan takeoff and calculate the vertical quantities one item at a time.

That back-and-forth is where quantities get lost, and it gets worse as drawing sets grow and fewer estimators carry more bids. Anything measured in plan only is short by every vertical foot in the job.

This guide explains the callouts, how to go through an elevation in six steps, what each trade takes from it and two worked examples.

157+ electrical estimators say The Takeoff AI saves them 90% of their estimating time. Plans are on The Takeoff AI pricing page.

elevation-view-drawing

What Is an Elevation Drawing?

An elevation drawing is a side view projected flat, so that every height on it can be measured. Exterior elevations show each face of a building, interior elevations show the walls of a room, and industrial sets add elevations of equipment, pipe racks and process structures. A section looks similar and differs in one way, which is that it cuts through the structure to show what is inside.

Elevation Callouts and Abbreviations

Elevation callouts give a height either above the floor or relative to a project datum, which is the reference level for the whole job.

CalloutMeaning
AFFAbove finished floor, the height of an item above the floor of its own room
FFEFinished floor elevation, the level of a floor relative to the datum
ELElevation relative to the datum, such as EL 112'-6"
TOSTop of steel
TOCTop of concrete
BOPBottom of pipe

Many projects set the first floor at EL 100'-0" so that levels below it never go negative.

elevation-drawing-callouts-example

How to Read an Elevation Drawing, Step by Step

Start by finding where the view was taken, then work from the datum to the callouts.

  1. Find the elevation marker on the plan, which shows the direction of the view and the sheet it is on.
  2. Check the scale, since elevations are often drawn at a different scale from the plan.
  3. Find the datum and the level lines for each floor.
  4. Note the callouts on the items in your scope.
  5. Subtract one elevation from another to get a height.
  6. Carry each height back to the plan takeoff.

What Each Trade Takes From an Elevation Drawing

Every trade uses elevations for the vertical part of its quantities.

  • Electrical estimators take the mounting heights of devices and panels, which set the length of every conduit drop.
  • Piping estimators take the bottom-of-pipe elevations and the vertical legs between a rack and the equipment.
  • Structural steel estimators take the top-of-steel elevations, which give column lengths.
  • Concrete estimators take wall and pier heights, which give volume and formwork area.
  • HVAC estimators take duct elevations and the vertical risers between floors.

Worked Examples

Electrical: Conduit Drops

A floor has 40 receptacles mounted at 18 inches AFF, fed from conduit above a 10-foot ceiling. Each drop is 10 feet minus 1.5 feet, which is 8.5 feet, so the drops add 340 feet of conduit and wire that a plan-only measurement leaves out. The same heights feed the feeder lengths taken from a riser diagram.

Piping: Vertical Legs

A line runs on a pipe rack at BOP EL 112'-6" and drops to a pump nozzle at EL 102'-0". The vertical leg is 10 feet 6 inches, and it adds two elbows to the takeoff as well as the pipe.

Common Mistakes

Three mistakes cause most errors with elevations.

  • AFF and EL get mixed, when one is measured from the room's floor and the other from the project datum.
  • The elevation is scaled at the plan's scale.
  • Bottom of pipe is treated as the centerline, which is off by half the pipe's diameter on every line.

How The Takeoff AI Handles Heights and Elevations

The Takeoff AI estimates from your drawings, counts each item in the scope and measures the runs between them by size, and it builds a 3D model from the 2D drawings, which puts the plan and elevation information in one place. The electrical takeoff Handbook page explains how conduit, cable and cable tray get counted.

The Takeoff AI is built on AI models trained on more than 1.2 million electrical and instrumentation (E&I) drawings. It counts devices, panels and fixtures, measures conduit, cable and cable tray lengths, splits the cable between tray and conduit, and picks up instruments from the instrument index. It delivers 95% accuracy, and every number is marked and highlighted on the drawing it came from, so someone can check it before the bid goes out.

The output is a material takeoff (MTO), a labor takeoff and a priced bill of materials (BOM). Estimators using it finish projects in 2 to 3 hours that used to take 30 to 40 hours, which saves 90 to 95% of their estimating time, and 157+ electrical estimators say The Takeoff AI saves them 90% of their time. It covers piping, piping and instrumentation diagrams (P&IDs), isometrics, mechanical, electrical and instrumentation, plumbing, HVAC including ductwork, structural steel, misc iron and concrete.

Joshua Nelson, Principal at Nelpro Project Solutions, says The Takeoff AI saves 95% of estimation time, and packages of more than 200 drawings across four disciplines now come back in hours where they used to take weeks.

Book a demo of The Takeoff AI.

Fewer Electrical Estimators, More Bids

The Bureau of Labor Statistics (BLS) counts about 221,400 cost estimators in the US and projects a 4% decline in that number by 2034, and roughly three in four estimator seats will need to be refilled over the decade, as The Shortage of Estimators report sets out. Heights are still carried from the elevation sheets to the plan takeoff by hand in most estimating departments, electrical ones included, and that can't hold with fewer estimators carrying more bids. Electrical contractors moving into data center work feel this first, as The Data Center Boom Has A Problem explains, and The Takeoff AI suits firms expanding into data centers.

FAQs

What Is an Elevation Drawing?

An elevation drawing is a flat side view of a building or structure with heights shown to scale. Estimators use it to get the vertical dimensions that a plan view cannot show.

What Is the Difference Between a Plan and an Elevation?

A plan looks down from above and shows length and width. An elevation looks from the side and shows height.

building-elevation-drawing

What Does AFF Mean on a Drawing?

AFF means above finished floor, the height of an item measured from the finished floor of the room it is in. A receptacle at 18 inches AFF sits 18 inches above that floor.

What Does EL 100'-0" Mean?

EL 100'-0" is an elevation of 100 feet relative to the project datum. Many projects assign it to the first floor so that levels below never carry negative numbers.

How Much Time Does The Takeoff AI Save on an Electrical Estimate?

157+ electrical estimators say The Takeoff AI saves them 90% of their time. Projects that used to take 30 to 40 hours are finished in 2 to 3 hours, with a material takeoff, a labor takeoff and a priced bill of materials at the end.

How Do I Check an AI Electrical Takeoff Before I Bid?

Every number in The Takeoff AI is marked and highlighted on the drawing it came from. The estimator opens any quantity, sees its source on the sheet and corrects it before the bid goes out.

Conclusion

Every trade's vertical quantities come from the elevations, and carrying them back to the plan takeoff is where they get lost. The work has stayed manual, and it can't stay that way with fewer electrical estimators carrying more bids. The Takeoff AI is the best electrical estimating software for contractors who need the takeoff done and priced in hours.