Research Report · September 2026
The State of Data Center Construction 2026

The Data Center Boom Has A Problem

Data centers are the only part of US construction still growing, and one contractor in six now has a piece of it, the highest share on record.

The other five are cutting staff, Texas has paused approvals, and half of this year's announced capacity is slipping.

None of that changes the fact that every package that goes ahead has to be priced by a desk that is losing people. This report is about that desk, and about what closes the gap.

  • Data center spend is up 79% in two years, while total construction is down 3.8%
  • One contractor in six has data center work, the highest share on record, and firms outside it are cutting staff
  • The estimator workforce is projected to shrink after 16,900 replacement openings a year
$84.1B
Data center construction starts, January to July 2026, nearly three times the same period of 2025
1 in 6
Contractors under contract on a data center, August 2026, the highest share ever recorded
16,900
Cost estimator openings a year through 2034, against a workforce projected to shrink
Sources: Construction starts data provider · Associated Builders and Contractors · Bureau of Labor Statistics · Full sources in the appendix
At a glance

The numbers that matter

+79%
Two-year growth in data center construction spend, April 2024 to April 2026
Census
−3.8%
Change in total US construction spending, July 2025 to July 2026. Nonresidential growth in July came entirely from data centers
Census · ABC
9.9 vs 8.3
Months of backlog, contractors with data center work against those without, August 2026
ABC
474 GW
Data center load in the Texas interconnection queue, frozen since 3 August pending a state audit
ERCOT
33%
Share of a liquid-cooled data center's cost that is mechanical, up from 22% for air-cooled builds
Turner & Townsend
12.3%
Contractors planning to cut staff in the next six months, the most since December. Firms without data center work are shedding headcount
ABC
82%
Contractors that cannot fill craft roles; 80% cannot fill salaried ones, the highest in three years
AGC
76%
Share of today's estimator seats that turn over by 2034
Our calculation · BLS base

White cards are third-party figures reported as published. The dark card is our own arithmetic from public data. Methodology and sources at the foot of the page.

The thesis

Every megawatt in this report was priced by a person before it was built. The industry is building more megawatts and hiring fewer of those people.

Spend rose 79% in two years while the rest of construction shrank. The estimator workforce is projected to fall. When a desk cannot get through a package on the deadline, the contractor passes, the work stays with the one in six who already have it, and the boom shows up in someone else's backlog. The slowdowns of the last two months change the timing of that pressure, not its direction. ContraVault AI exists to change which side of the line a desk sits on.

+79% / −4%
Data center construction spend, April 2024 to April 2026, against the projected change in US cost estimators, 2024 to 2034.
US Census Bureau · BLS
01

The Spend

The Census Bureau only started breaking data centers out as their own category in its Value of Construction Put in Place survey this year. The first clean reading came in April 2026: $50.7 billion at a seasonally adjusted annual rate (SAAR), which is a monthly figure scaled to what it would be over a full year. That passed general office construction ($43.8 billion) and the whole of public transportation construction for the first time.

April 2024 was $28.3 billion. April 2025 was $39.6 billion. April 2026 was $50.7 billion. No other private nonresidential category moved like that.

The July release, published 1 September, shows what is underneath. Total US construction spending was 3.8% below July 2025. Nonresidential spending edged up 0.1%, and ABC Chief Economist Anirban Basu said the increase was entirely due to data centers; take them out and nonresidential spending fell for a second month to its lowest level since September 2023. Data centers are not one growing category among many, they are the growing category.

Exhibit 1
Data center spend has grown 79% in two years
Annualized US private data center construction spend, April of each year, $ billion
April 2024
$28.3B
April 2025
$39.6B
April 2026
$50.7B
July update

Total construction spending down 3.8% year over year. Nonresidential up 0.1%, entirely on data centers. Everything else is at a three-year low.

Fig. 1 · Source: US Census Bureau, Monthly Construction Spending, June and September 2026 releases; ABC analysis, 1 September 2026
02

What Is Coming Next

Spend counts work already under way. The better signal for an estimating desk is what broke ground recently, because every one of those projects was priced months before the first pour, and the trade packages behind them are still being bid.

A construction starts data provider's September report puts data center starts through July at $84.1 billion across 136 projects, nearly three times the same period of 2025 and close to a quarter of all nonresidential building starts this year. July alone added $2.7 billion across 23 projects, led by a $1.5 billion CyrusOne campus in Texas.

CBRE's midyear count says the same from the other end. Capacity under construction across the eight primary North American markets hit a record 7,481 megawatts in the first half of 2026, with more than 80% already leased and vacancy at 1.4%. The work is sold before it is built.

Exhibit 2
Starts have not slowed down
Cumulative data center construction starts, $ billion
Jan to Apr 2025
$13.6B
Jan to Apr 2026
$49.5B
Jan to Jul 2026
$84.1B
Fig. 2 · Source: Construction starts data provider, June and September 2026 Data Center Reports
Exhibit 3
A record build, and still not enough
Capacity under construction, eight primary North American markets, megawatts
H2 2024 peak
6,350
H2 2025
5,994
H1 2026
7,481
Fig. 3 · Source: CBRE, North America Data Center Trends H1 2026
03

Where It Lands

Texas leads the country with 26 gigawatts of data center capacity under construction, per JLL data reported by the Houston Business Journal in August. Virginia, the market everyone still calls the largest, has 13. By dollar starts this year Texas ranks fifth at $9.9 billion through July, which says the Texas build is broad and already under way rather than freshly announced.

Louisiana is next door. Meta's Hyperion campus in Richland Parish has grown from a $10 billion announcement to a $27 billion program, built by Turner, DPR and Mortenson, with peak onsite employment expected above 5,000. Entergy will build ten gas-fired plants totaling 7.5 gigawatts to power it, a 30% increase to the state's grid. Every one of those plants is a piping and mechanical job.

It is landing on the corridor that already builds and maintains every refinery, LNG (liquefied natural gas) terminal and petrochemical plant on the Gulf Coast. BIC Magazine put it plainly in July: gigawatt-scale digital infrastructure is drawing from the same pool of pipefitters, electricians and welders the industrial sector has relied on for decades, and the data center industry alone is projected to need 140,000 more of them by 2030.

Exhibit 4
Texas is building twice what Virginia is
Data center capacity under construction, gigawatts, August 2026
Texas
26 GW
Virginia
13 GW
Fig. 4 · Source: JLL, via Houston Business Journal, 20 August 2026
Exhibit 5
One Louisiana campus, in the units a mechanical desk reads
Meta Hyperion, Richland Parish, as of March 2026
Program value
$27B
Gas plants to build
10 · 7.5 GW
Peak site workforce
5,000+
Fig. 5 · Source: Engineering News-Record and Fortune, March 2026; Entergy Louisiana
04

The Slowdown, And What It Slows

Two things have happened since midsummer that any honest version of this report has to carry. On 3 August, Governor Abbott froze new large-load interconnections in Texas until ERCOT (the Electric Reliability Council of Texas, the state grid operator) finishes an audit of every data center in its 474 gigawatt queue, a job ERCOT hopes to finish by December. On 21 September the freeze widened to every environmental permit a data center needs from the state. BloombergNEF put roughly 20% of the national pipeline at risk of delay from the Texas pause alone, and New York halted new approvals in July for up to a year.

The wider picture was already soft. Sightline Climate's count, reported by Bloomberg, says that of the roughly 12 gigawatts due online in the US this year, only about 5 were under construction, and up to half of the year's planned capacity could be delayed or cancelled. For 2027 the gap is wider, with 21.5 gigawatts announced and 6.3 under construction. More than a quarter of the 110 projects due in 2025 missed their dates. Transformers and switchgear run long, and local opposition has stopped projects in Wisconsin, Ohio, North Carolina and Virginia.

Read the slowdown for what it is. It is happening to the announced pipeline, at the power and permit gates, before a trade package exists. The 7,481 megawatts under construction are 80% leased and keep going, and starts through July are three times last year's. An audit that clears in December does not release projects one at a time, it releases a queue. The desks that will bid that queue are the ones with hours to spare when it lands.

Exhibit 6
Announced is not under construction
US data center capacity by scheduled year online, gigawatts, Sightline Climate count as reported April 2026
2026, announced
~12
2026, under construction
~5
2027, announced
21.5
2027, under construction
6.3
What it means for a desk

The projects that fall out never reached a bid table. The projects that survive the audit reach it together. A slowdown at the front of the pipeline is a bunching of packages at the back.

Fig. 6 · Source: Sightline Climate via Bloomberg and Axios, February to April 2026; Texas directives via Akin and Sidley client alerts, August and September 2026; BloombergNEF via Utility Dive, 6 August 2026
05

Who Has The Work

Here is the number that decides whether this boom reaches your desk. In July, ABC's Construction Backlog Indicator found 12% of contractors under contract on a data center, carrying 11.4 months of backlog against 7.5 for everyone else. The August reading, released 15 September, moved: roughly one in six members now has data center work, the highest share ABC has ever recorded, and the gap narrowed to 9.9 against 8.3 months. Basu's reading is that more firms are getting in, not that the work is thinning out.

The door is open, and the cost of staying outside it is visible in the same release. Firms without data center awards are cutting headcount, in the words of ABC economist Zack Fritz. The share of contractors planning to reduce staff in the next six months rose to 12.3%, the most since December. Only the largest contractors, above $100 million in revenue, saw backlog fall in August, and year-over-year gains are concentrated among firms under $30 million.

That is the opportunity in one sentence. The data center segment is admitting mid-size and smaller contractors at a record rate, and the mechanical, electrical, civil and specialty scopes that spill out of every campus are bid by the trades, one package at a time, on the same deadlines as everything else on the desk.

Exhibit 7
The gap narrowed because more firms got in
Construction backlog by contractor group, months
With data center work, Aug
9.9
With data center work, Jul
11.4
Without, Aug
8.3
Without, Jul
7.5
Fig. 7 · Source: Associated Builders and Contractors, Construction Backlog Indicator, July and August 2026
Exhibit 8
A record share of contractors now holds data center work
Share of ABC members under contract on a data center
July 2026
12%
August 2026
About 17% (1 in 6)
Reading it

Both groups need more estimating hours than they have. One is pricing the biggest packages it has ever seen. The other is cutting staff and chasing more bids to hold the same revenue.

Fig. 8 · Source: Associated Builders and Contractors, 11 August and 15 September 2026 releases

Get in while the door is openThe share of contractors with data center work went from one in eight to one in six in a month. See your own mechanical or electrical package counted and priced in hours, then check it line by line.

06

What The Package Looks Like

A data center is a power and cooling building. Turner & Townsend's cost index puts electrical at 54% of an air-cooled facility's cost and mechanical at 22%. Move to the liquid-cooled halls that AI racks need and mechanical rises to 33%, with electrical at 48%. JLL expects 80% of new facilities to be liquid-cooled by 2030.

That mechanical third is chilled water, coolant distribution loops, secondary pumping, dry coolers, generator fuel and fire suppression. In estimating terms it is process piping, the scope that takes longest to count on any industrial desk. The electrical half is switchgear, busway, cable tray, conduit and the instrumentation that ties it together. Between them, roughly four fifths of a data center's construction value sits in the two scopes that carry the most line items per sheet.

The package is also getting more expensive to get wrong. JLL puts shell-and-core cost at $10.7 million per megawatt in 2025, up from $7.7 million in 2020, with a further 6% rise expected this year. AI-optimized halls run past $20 million per megawatt. Equipment lead times average 42 weeks, and 57% of 2025 projects slipped at least three months.

Exhibit 9
Liquid cooling moves a third of the job to mechanical
Share of facility construction cost by discipline
Electrical, air-cooled
54%
Electrical, liquid-cooled
48%
Mechanical, air-cooled
22%
Mechanical, liquid-cooled
33%
Fig. 9 · Source: Turner & Townsend, Data Centre Construction Cost Index 2025-2026
Exhibit 10
The cost of each megawatt keeps climbing
Shell-and-core data center construction cost, $ million per megawatt
2020
$7.7M
2025
$10.7M
2026, expected
$11.3M
AI-optimized hall
$20M+
Fig. 10 · Source: JLL, 2026 Global Data Center Outlook
Where ContraVault AI helps

Four fifths of the job, counted and priced in hours

ContraVault AI reads the piping and instrumentation diagrams, isometrics and drawing sets in a package and returns the takeoff and the priced estimate together, every line, fitting, valve, cable run and device traced back to the sheet it came from. It covers the mechanical and piping scope and, as of this month, the electrical and instrumentation scope as well. The estimator checks a first pass instead of building one.

That is the difference between a desk that can take the data center package this month and a desk that has to pass on it.

07

The Moving Target

A data center package does not hold still long enough to be priced once. Hyperscalers have compressed design-to-construction timelines so far that a scope change which used to take months to process now moves in weeks, and the change that matters most is cooling. Switching a hall from air to liquid mid-build means secondary steel for the piping loops, facility water filtration, revised electrical loads and rerouted mechanical and electrical paths, with crews already on site. One colocation developer described a customer cutting a campus from nine liquid-cooled halls to seven partway through deployment because network capacity mattered more than GPU processing.

The numbers on that volatility are blunt. Projects whose design is frozen early see change orders of roughly 3% to 5% of contract value. Guaranteed maximum price contracts signed on incomplete design run 8% to 14%. The average data center started this year costs $1.06 billion and 701,000 square feet, against $352.8 million and 454,400 square feet in 2025, and cost per square foot has climbed 57% in a year to $818, with individual projects anywhere from under $300 to over $2,200. Average hyperscale build time has stretched from about 12 months to 18 to 24. A delay on a 60 megawatt facility costs its owner around $14 million a month, which is why liquidated damages now flow straight to the contractor.

The competitive side is just as unforgiving. Hyperscalers lock design-build contracts as much as 24 months before groundbreaking with a handful of tier-one builders, one of which carries a record $44 billion backlog with roughly 40% of it data centers. Bonds run to 100% of contract value. Owners have told the trade press they do not want a low first number with change orders dragging behind it; they want an estimate that reads as a technical document. And the same reporting notes that the largest firms are passing on work in other sectors that still needs bidders, which is where the door for mid-size contractors opens.

For a desk, this means the package will be priced more than once, and the second and third passes come with less time than the first. A team that needs a working week to count a mechanical or electrical scope cannot re-price it when the cooling spec moves. A team that can rerun the takeoff and the estimate from the revised set, and see exactly what changed, can.

Exhibit 11
Unfrozen design triples the change-order load
Change orders as a share of contract value, by design state at signing
Design frozen early
3% to 5%
GMP on incomplete design
8% to 14%
Fig. 11 · Source: Construction software provider analysis of 2026 AI data center bids, July 2026, citing JLL and BloombergNEF
Exhibit 12
The same square foot can cost seven times more
Data center construction cost per square foot, projects started January to July 2026
Low end
under $300
Average
$818
High end
over $2,200
Reading it

The average is up 57% on 2025. A square-foot rate from last year's colocation job underprices an AI hall by hundreds of dollars a foot before the first change order.

Fig. 12 · Source: Construction starts data provider, September 2026 Data Center Report

Price it again, not from scratchWhen the cooling spec moves, the estimate moves with it. See a package re-counted and re-priced from a revised set, with every changed quantity flagged for you to check.

08

The Price Of The Miss

Costs are moving under the estimate while it sits on the desk. AGC's August 2026 analysis of BLS producer price data shows construction input costs up 7.1% year over year while bid prices rose 3.5%. Nearly half of Turner & Townsend's respondents reported bid or tender price increases of 6% to 15% in the past year, and another 21% saw more than 15%.

AGC's outlook found 70% of contractors were affected by tariffs in 2025. Forty percent raised bid prices, a third pulled materials purchases forward, and 11% absorbed most or all of the cost themselves. A number that was right when the package arrived can be wrong by the time it is submitted.

At $10.7 million per megawatt, a contingency added to cover what a rushed team could not see is worth millions on a single hall. It is rational protection, and it is also the reason a thinner desk loses to the desk that could count everything.

Exhibit 13
Costs are rising twice as fast as bid prices
Year-over-year change, July 2025 to July 2026
Construction input costs
+7.1%
Bid prices
+3.5%
Fig. 13 · Source: Associated General Contractors analysis of BLS producer price index data, August 2026

Price it before the number movesA package that sits a week on a busy desk is priced against last week's costs. ContraVault AI returns the takeoff and the estimate together, so the number goes out while it is still right.

09

The People Who Price It

BLS counts 221,400 cost estimators in the United States as of 2024 and projects 212,100 by 2034. Over the same decade it expects 16,900 openings a year, every one of them a replacement for someone retiring or leaving the profession. Run the arithmetic and 76% of today's seats turn over by 2034.

The wider trades are in the same position. ABC's January model says construction must attract 349,000 net new workers in 2026 to keep up, rising to 456,000 in 2027. AGC's outlook found 82% of firms struggling to fill craft roles and 80% struggling to fill salaried ones, the highest share in three years, and 60% had postponed or cancelled a project in the past six months because of staffing. McKinsey estimates 20 skilled trade openings for every new entrant through 2032.

September's ABC release adds the newest turn. Construction job openings are near a two-year high, ABC's confidence reading for staffing fell even as sales and margins rose, and Basu's summary was that labor scarcity is re-emerging as a major headwind. Hiring will not close this. The desks that get into the data center work will be the ones that get more packages out of the estimators they already have.

Exhibit 14
Four in five firms cannot fill the seats they have
Share of contractors reporting difficulty filling positions, 2026 outlook
Craft roles
82%
Salaried roles
80%
Delayed or cancelled a project for staffing
60%
Fig. 14 · Source: Associated General Contractors and Sage, 2026 Construction Hiring and Business Outlook
Exhibit 15
Three quarters of the seats turn over in a decade
16,900 openings × 10 years ÷ 221,400 employed in 2024
Employed, 2024
221,400
Projected, 2034
212,100
Seats turning over
169,000 · 76%
Fig. 15 · Source: BLS Occupational Outlook Handbook, cost estimators; our calculation
10

The Preconstruction Chokepoint

Most coverage of the boom stops at power, permits and craft labor, and the last two months have given it plenty of both. A May 2026 piece in For Construction Pros made the point this report is built on: before any of those constraints bite, someone has to price the job accurately enough to pursue it, and the preconstruction teams doing that have not scaled with the volume.

The mechanism compounds. A contractor who cannot price a complex package on the deadline passes on it. Every firm that walks away removes price tension from the market. The bids that do go in carry wider margins to cover what the team could not see, and at data center values that padding is structural inflation. Incomplete takeoffs then generate rework, revise, clarify and rebid, before a foundation is poured.

Contractors know where the leverage is. AGC's outlook found 61% of firms using or planning to invest more in AI, up from 44% a year earlier, and estimating was one of the two most common places they put it, alongside preconstruction. Twenty-three percent already use it for estimating.

Exhibit 16
Where contractors are putting AI first
Share of firms using or planning to increase investment in AI, AGC 2026 outlook
2025 outlook
44%
2026 outlook
61%
Using it for estimating
23%
What it does not do

Software does not make the bid decision. On a data center package the estimator still owns the scope read and the risk call. What software can take is the counting and the pricing pass, with every number traceable so the estimator can check it.

Fig. 16 · Source: Associated General Contractors and Sage, 2026 Construction Hiring and Business Outlook

Stop passing on packagesIf your desk turned down a data center or industrial package this quarter, that is the package to bring. We count and price it while you watch, then you check it.

11

The Scissors

Put the curves together. Data center construction spend rose 79% in two years while everything else in construction fell. The estimator workforce is projected to shrink 4% over the coming decade, with three quarters of the seats changing hands along the way. One contractor in six is now inside the data center work, a record, and the rest are cutting staff. The Texas queue is frozen until an audit clears, and when it clears the packages come at once, and each of them will be priced more than once before it is awarded.

The gap will not close by hiring, because there is nobody to hire. The only variable a contractor controls this year is how many hours a package takes to count and price, and on a data center package that is mostly pipe and cable.

That is exactly the variable ContraVault AI moves. The takeoff and the estimate come back together, every quantity traced to its sheet, the estimator checks it rather than building it, and the same desk gets through more packages in the same week. More packages priced is more data center work bid, and more work bid is the only way onto the right side of the line.

Exhibit 17
More packages, fewer people to price them
Indexed to 2024 = 100. Data center spend from Census, April of each year. Estimator headcount from the BLS 2024 to 2034 projection, spread evenly across the decade
202420252026100140179Data center spend99.699.2THE GAP80 points in two yearsEstimator headcount, BLS projection (grey)Data center construction spend, Census (white)
Fig. 17 · Source: US Census Bureau; BLS Occupational Outlook Handbook; our construction. Headcount points are interpolated from the BLS decade projection, not measured yearly
This week

One thing to do before the next package lands

The next data center or industrial package that reaches your desk, log two numbers: the estimator-hours the mechanical, piping and electrical takeoff took, and whether the desk could take the same package again next month without dropping something else.

Two packages in, you have the number this report cannot give you, in the unit you control. Then bring one of them to a walkthrough and see the same package come back counted and priced.

MeasureWhere it standsDirection
Data center construction spend$50.7B SAAR, +79% in two yearsRising, while total construction is down 3.8%
Data center starts, year to date$84.1B through July, nearly 3x 2025Rising
Contractors under contract on a data centerAbout 1 in 6, up from 1 in 8 in JulyWidening, a record
Texas interconnection queue474 GW, frozen pending audit, target DecemberPaused, then released as a batch
Change orders on unfrozen design8% to 14% of contract valueRising with liquid cooling
Mechanical share of a liquid-cooled hall33%, up from 22% air-cooledRising
Cost estimators employed221,400, to 212,100 by 2034Falling
Estimator seat turnover by 203476% (calculated)Compounding
Contractors planning staff cuts12.3%, most since DecemberRising, outside the data center segment
Sayan Sen
Founder and CEO, ContraVault AI

Every contractor we talk to on the Gulf Coast has the same two problems in the same week. A data center package they cannot staff and a refinery turnaround they cannot afford to lose. The estimator is the same person in both meetings. We built ContraVault AI so that person gets through the counting in hours and spends the week on the judgment nobody else in the building can do.

Where ContraVault AI fits

The projects are not slowing down where it matters. The hiring is not catching up. The desk is where this gets solved.

ContraVault AI reads piping and instrumentation diagrams, isometrics and drawing sets and returns the takeoff and the priced estimate together, every quantity traceable to its source sheet, across piping, mechanical, electrical and instrumentation. The estimator checks it and the package you would have passed on gets bid.

Bring that package. It is the one where the difference shows.

Sources and methodology
  1. US Census Bureau, Monthly Construction Spending, April 2026 (released 1 June 2026) and July 2026 (released 1 September 2026); April figures as reported by Bloomberg and Data Center Knowledge; July analysis by Associated Builders and Contractors, 1 September 2026.
  2. Construction starts data provider, June 2026 and September 2026 Data Center Reports, prepared by its chief economist and associate economist; per-project and per-square-foot cost figures from the September edition.
  3. CBRE, North America Data Center Trends H1 2026, and the H2 2025 edition for the 5,994 MW year-end figure.
  4. JLL, data center capacity under construction by state, reported by Houston Business Journal, 20 August 2026; JLL 2026 Global Data Center Outlook for cost per megawatt, lead times, delay rates and liquid-cooling adoption.
  5. Engineering News-Record and Fortune, March 2026, on Meta Hyperion and the Entergy generation program.
  6. Sightline Climate data on announced versus under-construction capacity, as reported by Bloomberg (April 2026) and Axios (February 2026); Data Center Watch (10a Labs) on cancelled and delayed projects, as reported by S&P Global, January 2026.
  7. Texas Governor's directives of 3 August and 21 September 2026, as summarized in Akin Gump (7 August) and Sidley Austin (23 September) client alerts; ERCOT audit timeline and BloombergNEF pipeline estimate via Utility Dive, August 2026; Texas Tribune, 14 August 2026.
  8. Associated Builders and Contractors, Construction Backlog Indicator and Construction Confidence Index, July 2026 (released 11 August) and August 2026 (released 15 September), including Construction Dive coverage of 16 September; the 349,000-worker model, January 2026.
  9. Associated General Contractors and Sage, 2026 Construction Hiring and Business Outlook (8 January 2026); AGC analysis of BLS producer price index data, August 2026.
  10. Turner & Townsend, Data Centre Construction Cost Index 2025-2026, including bid price findings as reported by Quartz.
  11. Change-order ranges, build-time and GMP composition from a construction software provider's analyses of 2026 US and global data center construction, April and July 2026; mid-build cooling change effects from a construction ERP provider's June 2026 note; the nine-to-seven halls example from a colocation developer's 2026 outlook, April 2026; owner and contractor comments from Engineering News-Record, August 2026; tier-one backlog concentration from Capacity Media, May 2026; delay cost per month from a project controls provider, January 2026.
  12. BIC Magazine, Gulf Coast Talent Clash, July 2026, including the McKinsey trade-entrant ratio and the 140,000-worker projection.
  13. US Bureau of Labor Statistics, Occupational Outlook Handbook, Cost Estimators (2024 base, 2034 projection).
  14. ContraVault AI, The Shortage of Estimators, August 2026.

The 76% turnover figure is our calculation: 16,900 annual openings × 10 years ÷ 221,400 employed in 2024. Exhibit 17 indexes Census spend and the BLS decade projection to 2024; the headcount points are interpolated. Third-party figures are reported as published; publication dates vary.

Co-published with RFP Professionals · September 2026