What Is a Piping System?
What is a piping system? It is every part needed to move a fluid safely: the pipe, the fittings that change direction or size, the flanges and gaskets that join pieces that need to come apart, the valves that control flow, and the supports that hold it all up. Piping in construction is designed by engineers, shown on P&ID (piping and instrumentation diagram) drawings and isometrics, and built by pipefitters and welders.
What Is Process Piping?
Process piping carries the fluids a facility makes or uses, in refineries, chemical plants, power plants, food and pharmaceutical plants and data centers. ASME B31.3 sets the rules for its design, materials, welding and testing. Process piping systems are usually carbon or stainless steel, welded or flanged, and they are the largest piping scope on most industrial jobs. The ASME B31.3 for estimators entry covers what the code changes on a bid.
Other Common Piping Systems
What is hydronic piping? It is the closed loop of hot or chilled water that heats and cools a building, running between boilers, chillers, pumps and coils. What is fuel gas piping? It is the piping that carries natural gas or propane to burners and equipment, built to NFPA 54. Plumbing and fire protection piping round out most commercial jobs.
Pipe Sizes and Schedules
What is IPS piping? IPS stands for iron pipe size, the nominal size system that steel pipe and many plastic pipes are made to, where the outside diameter stays fixed for each size. What is schedule in piping? The schedule sets the wall thickness, so Schedule 40 and Schedule 80 pipe of the same size share an outside diameter but differ in wall and weight. The pipe schedule chart lists both.
Piping Components and How Each Is Counted
| Component | How It Is Counted |
|---|---|
| Pipe | Feet, by size, schedule and material |
| Fittings | Each, by type, size and schedule |
| Flanges | Each, by type, size and pressure class |
| Valves | Each, by type, size, class and end connection |
| Gaskets and bolts | One set per flanged joint |
| Welds | Each, then in diameter inches for labor |
| Supports | Each, by type, from the support drawings |
| Insulation | Feet, by pipe size and thickness |
Bolt and gasket counts follow the flanges, and the flange bolt chart lists bolt counts by size and class.
How Piping Gets Estimated
Piping estimate = material (pipe, fittings, flanges, valves, bolts, gaskets, supports) + labor (welds, handling, erection, testing)
Estimators take off the piping from the isometrics, use the P&IDs and line list to confirm sizes, materials and valves, and use the piping specification to set the schedule and class. Material is priced from the count, and labor is priced from welds in diameter inches, plus handling, erection and testing. On a large job, the takeoff alone can take an estimator 40 to 50 hours.
Common Mistakes on a Piping Takeoff
- Counting pipe but leaving bolts and gaskets to an allowance
- Missing small-bore drains, vents and instrument connections
- Taking the schedule from the line instead of the piping specification
- Leaving out supports shown only on the support drawings
- Pricing every weld at one rate instead of by diameter inches
How The Takeoff AI Handles Piping
The Takeoff AI estimates the P&ID (piping and instrumentation diagram) drawings, isometric drawings, line lists and the specification, and takes off the piping end to end. It counts every pipe length, fitting, flange, valve, bolt, gasket, support and weld, and prices the material takeoff (MTO) and labor takeoff (LTO) into a priced bill of materials (BOM) at your own rates. It also flags where the drawings, the specification and the scope of work do not match, and builds a 3D model from the 2D drawings.
Every quantity is highlighted on the sheet it came from, and it is trained on more than 1 million drawing sets and runs at 95% accuracy. 113 estimators say The Takeoff AI is the best piping estimating software they have used, and it helps them estimate projects in 3 to 4 hours that once took 40 to 50 hours. See it on the piping page.