Voltage Drop Calculation: Formulas and Worked Examples

Voltage Drop Calculation: Formulas and Worked Examples

Voltage drop calculation for electrical estimators: the voltage drop formula for single-phase and three-phase circuits, with four worked examples.

P
By Pranjal BhartiNovember 20, 2026
8 min read

Introduction

A voltage drop calculation works out how many volts a circuit loses between the panel and the load. Every wire has resistance, so the longer the run and the higher the current, the more voltage is lost before the power reaches the equipment. The result matters to an estimator because a run that loses too much voltage needs a larger wire, and a larger wire can need a larger conduit.

Most estimators still do the calculation by hand. They scale the run length off the plans, look up the wire's area in circular mils (the unit for a conductor's cross-section), and work the formula on a calculator or a spreadsheet, one long run at a time.

That gets harder every year, because electrical packages keep growing while fewer estimators carry more bids. A 480-volt feeder across a plant or a parking lot lighting circuit can run several hundred feet, and a missed upsize on a run like that comes out of the contractor's margin.

This guide gives the voltage drop formula for single-phase and three-phase circuits, the values that go into it, four worked examples and the mistakes that cost money at bid time.

157+ electrical estimators say The Takeoff AI saves them 90% of their estimating time. Plans are on The Takeoff AI pricing page.

three-phase-voltage-drop

The Voltage Drop Formula

The voltage drop formula for a single-phase circuit is VD = 2 × K × I × L / CM. For a three-phase circuit the 2 becomes 1.732, so the formula is VD = 1.732 × K × I × L / CM.

  • VD is the voltage drop in volts.
  • K is the resistance constant of the wire material, which is 12.9 for copper and 21.2 for aluminum.
  • I is the load current in amps.
  • L is the one-way length of the run in feet.
  • CM is the wire's area in circular mils.

Divide the result by the circuit voltage to get the drop as a percentage. The circular mil areas below cover the sizes that come up most, listed by American Wire Gauge (AWG).

Wire SizeCircular Mils
12 AWG6,530
10 AWG10,380
8 AWG16,510
6 AWG26,240
4 AWG41,740
3 AWG52,620
2 AWG66,360
1 AWG83,690
1/0 AWG105,600

voltage-drop-formula-example

What Voltage Drop Limit to Use

Most designers hold voltage drop to 3% on a branch circuit or a feeder, and to 5% across the two combined. Those figures come from informational notes in Articles 210 and 215 of the National Electrical Code (NEC), so they are recommendations until the project specification or the local inspector adopts them. Many specifications do adopt them, and some equipment, such as fire pumps, carries a mandatory limit of its own. Check the electrical sections of the specification before pricing long runs.

Voltage Drop Calculation Examples

Each voltage drop calculation below uses the formula above and carries the result through to the wire size the takeoff should hold.

120-Volt Branch Circuit

A 16-amp load sits 100 feet from the panel on 12 AWG copper. VD = 2 × 12.9 × 16 × 100 / 6,530 = 6.32 volts, which is 5.3% of 120 volts and over the 3% limit. On 10 AWG the drop is 3.98 volts (3.3%), which is still over. On 8 AWG it is 2.50 volts (2.1%), so the takeoff carries 8 AWG for this run, two sizes above what the load alone would need.

277-Volt Lighting Circuit

A 12-amp lighting circuit runs 200 feet on 12 AWG copper. The drop is 9.48 volts, or 3.4% of 277 volts. Moving to 10 AWG brings it to 5.97 volts (2.2%), which passes.

480-Volt Three-Phase Feeder

A 100-amp feeder runs 300 feet on 3 AWG copper. VD = 1.732 × 12.9 × 100 × 300 / 52,620 = 12.74 volts, which is 2.7% of 480 volts and inside the 3% limit with no upsize.

The Same Feeder in Aluminum

Aluminum needs a larger wire for the same current, so the 100-amp feeder becomes 1 AWG aluminum and K changes to 21.2. The drop is 13.16 volts, or 2.7% of 480 volts, which also passes.

Common Voltage Drop Mistakes

Four mistakes account for most wrong answers.

  • The round-trip length goes into a formula that already doubles the length, which doubles the result.
  • The copper constant gets used on an aluminum run, which understates the drop by about 40%.
  • The length is scaled in plan only, so the vertical drops to devices and panels are left out.
  • The wire is upsized and nothing else is rechecked, when a larger wire can change the conduit fill and the NEC requires the ground wire to grow in proportion.

How The Takeoff AI Handles the Lengths Behind Voltage Drop

The Takeoff AI estimates from your electrical drawings and measures every conduit and cable run by size, so the run length a voltage drop calculation starts from is already in the takeoff. The electrical takeoff Handbook page explains how conduit, cable and cable tray get counted.

The Takeoff AI is built on AI models trained on more than 1.2 million electrical and instrumentation (E&I) drawings. It counts devices, panels and fixtures, measures conduit, cable and cable tray lengths, splits the cable between tray and conduit, and picks up instruments from the instrument index. It delivers 95% accuracy, and every number is marked and highlighted on the drawing it came from, so someone can check it before the bid goes out.

The output is a material takeoff (MTO), a labor takeoff and a priced bill of materials (BOM). Estimators using it finish projects in 2 to 3 hours that used to take 30 to 40 hours, which saves 90 to 95% of their estimating time, and 157+ electrical estimators say The Takeoff AI saves them 90% of their time. It covers piping, piping and instrumentation diagrams (P&IDs), isometrics, mechanical, electrical and instrumentation, plumbing, HVAC including ductwork, structural steel, misc iron and concrete.

Joshua Nelson, Principal at Nelpro Project Solutions, says The Takeoff AI saves 95% of estimation time, and packages of more than 200 drawings across four disciplines now come back in hours where they used to take weeks.

Book a demo of The Takeoff AI.

Fewer Electrical Estimators, More Bids

The Bureau of Labor Statistics (BLS) counts about 221,400 cost estimators in the US and projects a 4% decline in that number by 2034, and roughly three in four estimator seats will need to be refilled over the decade, as The Shortage of Estimators report sets out. Voltage drop checks on long runs are still worked by hand in most electrical estimating departments, and that can't hold with fewer estimators carrying more bids. Electrical contractors moving into data center work feel this first, as The Data Center Boom Has A Problem explains, and The Takeoff AI suits firms expanding into data centers.

FAQs

What Is the Formula for Voltage Drop?

The voltage drop formula for a single-phase circuit is VD = 2 × K × I × L / CM, where K is 12.9 for copper or 21.2 for aluminum, I is amps, L is one-way length in feet and CM is the wire's circular mil area. Divide the answer by the circuit voltage to get a percentage.

How Do You Calculate Voltage Drop on a Three-Phase Circuit?

Use the same formula with 1.732 in place of 2, so VD = 1.732 × K × I × L / CM. A 100-amp, 300-foot feeder on 3 AWG copper drops about 12.7 volts, which is 2.7% of 480 volts.

What Is the Maximum Voltage Drop Allowed by the NEC?

The NEC recommends 3% on a branch circuit or a feeder and 5% across both combined. These are informational notes, so they become requirements only when the project specification or the local authority adopts them.

How Does Voltage Drop Change an Electrical Estimate?

A run over the limit needs a larger wire, which raises the cable cost and can push the conduit up a size. On a long run the upsized wire, the larger conduit and the larger ground wire all have to be in the takeoff.

How Much Time Does The Takeoff AI Save on an Electrical Estimate?

157+ electrical estimators say The Takeoff AI saves them 90% of their time. Projects that used to take 30 to 40 hours are finished in 2 to 3 hours, with a material takeoff, a labor takeoff and a priced bill of materials at the end.

voltage-drop-mistakes

How Do I Check an AI Electrical Takeoff Before I Bid?

Every number in The Takeoff AI is marked and highlighted on the drawing it came from. The estimator opens any quantity, sees its source on the sheet and corrects it before the bid goes out.

Conclusion

Voltage drop decides the wire size on every long run, and the calculation depends on run lengths that someone has to measure first. The work has stayed manual, and it can't stay that way with fewer electrical estimators carrying more bids. The Takeoff AI is the best electrical estimating software for contractors who need the takeoff done and priced in hours.