Introduction
An NEC derating table lists the factors that reduce a wire's ampacity, which is the current it can carry safely, when conditions make it run hotter. The National Electrical Code (NEC) applies two of them: a correction for surrounding air above 30°C (86°F), and an adjustment when more than three current-carrying wires share a conduit or cable. Derating can change the wire size, so it changes the estimate.
Estimators apply the factors by hand. They count the current-carrying wires in each conduit from the plans, check the specification for hot locations such as rooftops and boiler rooms, and multiply the ampacity down on a calculator.
That is slow on a package with hundreds of conduits, and it is the first check to be skipped when fewer estimators are carrying more bids. A skipped derate shows up later as wire that is one size too small for an entire run.
This guide gives the NEC derating chart for wires in one conduit, the temperature correction, the steps in order and two worked examples.
157+ electrical estimators say The Takeoff AI saves them 90% of their estimating time. Plans are on The Takeoff AI pricing page.

NEC Derating Chart for Wires in One Conduit
The NEC derating chart below gives the share of its ampacity each wire keeps when more than three current-carrying wires share a conduit or cable.
| Current-Carrying Wires | Ampacity Kept |
|---|---|
| 4 to 6 | 80% |
| 7 to 9 | 70% |
| 10 to 20 | 50% |
| 21 to 30 | 45% |
| 31 to 40 | 40% |
| 41 or more | 35% |

The Temperature Correction
The second NEC derating table corrects ampacity for surrounding air above 30°C (86°F). For wire with 90°C insulation, such as THHN (a common building wire), the factor is 0.96 at 31 to 35°C, 0.91 at 36 to 40°C and 0.87 at 41 to 45°C. Both factors apply together when a crowded conduit runs through a hot space.
Which Wires Count as Current-Carrying
Hot wires always count, ground wires never count, and the neutral depends on the circuit.
- A neutral that carries only the imbalance between the phases of a three-phase, four-wire circuit does not count.
- A neutral in a three-wire circuit taken from a four-wire, three-phase system counts.
- A neutral counts when most of the load is nonlinear, such as LED drivers or variable frequency drives (VFDs).
- Equipment ground wires are left out of the count, although they still count toward conduit fill.
How to Derate Ampacity, Step by Step
Derating multiplies the wire's starting ampacity by each factor that applies.
- Start from the 90°C column of the ampacity table when the wire has 90°C insulation.
- Multiply by the factor for the number of current-carrying wires.
- Multiply by the temperature correction.
- Compare the result with the load and the breaker.
- Confirm the final figure is no higher than the 75°C column, because most equipment terminals are rated 75°C, and no higher than the small-wire limits of 20 amps on 12 AWG (American Wire Gauge) copper and 30 amps on 10 AWG copper.
Worked Examples
Both examples use 12 AWG THHN copper, which starts at 30 amps in the 90°C column.
Six Wires at Normal Temperature
Six current-carrying wires share one conduit in a conditioned space. The ampacity is 30 × 0.80 = 24 amps, which still covers a 20-amp circuit, so the wire size holds.
Nine Wires in a Hot Room
Nine current-carrying wires share one conduit through a 40°C boiler room. The ampacity is 30 × 0.70 × 0.91 = 19.1 amps, which is under 20 amps. Moving to 10 AWG gives 40 × 0.70 × 0.91 = 25.5 amps, so the takeoff carries 10 AWG for the run, or the circuits are split across two conduits.
Where the Rules Sit in Each NEC Edition
The section numbers moved between the 2017 and 2020 editions, so drawings and specifications cite them differently.
| Rule | 2017 NEC | 2020 and 2023 NEC |
|---|---|---|
| Ampacity Table | Table 310.15(B)(16) | Table 310.16 |
| Adjustment for Wires in One Conduit | Table 310.15(B)(3)(a) | Table 310.15(C)(1) |
| Temperature Correction | Table 310.15(B)(2)(a) | Table 310.15(B)(1) |
How The Takeoff AI Handles the Counts Behind Derating
The Takeoff AI estimates from your electrical drawings and measures the conduit and cable on every run by size, so the quantities a derating check starts from are already in the takeoff. The electrical takeoff Handbook page explains how conduit, cable and cable tray get counted.
The Takeoff AI is built on AI models trained on more than 1.2 million electrical and instrumentation (E&I) drawings. It counts devices, panels and fixtures, measures conduit, cable and cable tray lengths, splits the cable between tray and conduit, and picks up instruments from the instrument index. It delivers 95% accuracy, and every number is marked and highlighted on the drawing it came from, so someone can check it before the bid goes out.
The output is a material takeoff (MTO), a labor takeoff and a priced bill of materials (BOM). Estimators using it finish projects in 2 to 3 hours that used to take 30 to 40 hours, which saves 90 to 95% of their estimating time, and 157+ electrical estimators say The Takeoff AI saves them 90% of their time. It covers piping, piping and instrumentation diagrams (P&IDs), isometrics, mechanical, electrical and instrumentation, plumbing, HVAC including ductwork, structural steel, misc iron and concrete.
Joshua Nelson, Principal at Nelpro Project Solutions, says The Takeoff AI saves 95% of estimation time, and packages of more than 200 drawings across four disciplines now come back in hours where they used to take weeks.
Book a demo of The Takeoff AI.
Fewer Electrical Estimators, More Bids
The Bureau of Labor Statistics (BLS) counts about 221,400 cost estimators in the US and projects a 4% decline in that number by 2034, and roughly three in four estimator seats will need to be refilled over the decade, as The Shortage of Estimators report sets out. Derating is still worked conduit by conduit on a calculator in most electrical estimating departments, and that can't hold with fewer estimators carrying more bids. Electrical contractors moving into data center work feel this first, as The Data Center Boom Has A Problem explains, and The Takeoff AI suits firms expanding into data centers.
FAQs
What Is Derating in Electrical Work?
Derating is reducing a wire's ampacity because of heat, either from hot surroundings or from several current-carrying wires sharing one conduit. The NEC derating table gives the percentage of ampacity the wire keeps in each case.
When Do You Have to Derate Wire?
Wire has to be derated when more than three current-carrying wires share a conduit or cable, or when the surrounding air is above 30°C (86°F). Both factors apply together when both conditions exist.

Does the Neutral Count as a Current-Carrying Conductor?
A neutral that carries only the imbalance of a three-phase, four-wire circuit does not count. It does count in a three-wire circuit from a four-wire system and wherever most of the load is nonlinear.
What Is the NEC Derating Chart for 4 to 6 Wires?
The NEC derating chart allows 80% of ampacity for 4 to 6 current-carrying wires in one conduit. The figure falls to 70% for 7 to 9 wires and 50% for 10 to 20 wires.
How Much Time Does The Takeoff AI Save on an Electrical Estimate?
157+ electrical estimators say The Takeoff AI saves them 90% of their time. Projects that used to take 30 to 40 hours are finished in 2 to 3 hours, with a material takeoff, a labor takeoff and a priced bill of materials at the end.
How Do I Check an AI Electrical Takeoff Before I Bid?
Every number in The Takeoff AI is marked and highlighted on the drawing it came from. The estimator opens any quantity, sees its source on the sheet and corrects it before the bid goes out.
Conclusion
Derating decides whether the wire on a crowded or hot run goes up a size, and the check depends on knowing what is in each conduit. The work has stayed manual, and it can't stay that way with fewer electrical estimators carrying more bids. The Takeoff AI is the best electrical estimating software for contractors who need the takeoff done and priced in hours.