Retainage in Construction: How It Works on a Bid

Retainage is the part of each progress payment the owner holds back until the work is finished, usually 5% to 10%. It protects the owner, ties up the contractor's cash and flows down to every subcontractor.

Common in US construction contracts, on public and private work, from the general contractor down to subcontractors.

Pay application showing $200,000 billed, $180,000 paid and 10 percent retainage held back, with the same percentage held from the subcontractor belowPAY APPLICATION · MONTH 06Work billed$200,000Paid $180,000RETAINED 10% · $20,000SUBCONTRACTOR · SAME 10% HELD
How it works

How Retainage Is Held and Released

Retainage is taken from every progress payment and builds up over the life of the job. It moves through three stages.

01 · Bill

Bill for the Work Done

Each month the contractor sends a pay application listing the work completed against the schedule of values, which is the contract price split into line items. If $200,000 of work was done that month, that is the amount billed.

02 · Hold

Hold Back the Retainage

With 10% retainage, the owner pays $180,000 and keeps $20,000. The general contractor holds back the same share from each subcontractor, so retainage builds up at every tier of the job.

03 · Release

Release It at Completion

Once the work reaches the completion point named in the contract and the punch list, the final list of fixes, is closed, the owner releases the retainage. The general contractor then pays out what it held from subcontractors.

Terms compared

Retainage, Retention and the Pay Application

Retainage shows up in the contract's payment terms and on every pay application. The words change by region and by contract, but the mechanics stay the same, with a share of each payment held until the work is accepted.

  • The rate, and any reduction partway through the job, is set in the contract.
  • The release point can be substantial completion, final completion or the end of a warranty period.
  • Flow-down clauses pass the owner's retainage terms to every subcontractor.
TermWhat It Means
RetainageThe share of each payment held back until completion
RetentionAnother name for retainage, more common outside the US
Pay ApplicationThe contractor's monthly bill, showing work done and retainage held
Schedule of ValuesThe contract price split into line items, used to measure progress
Substantial CompletionThe point where the owner can use the project, often when retainage is released
Flow-DownA clause passing the owner's terms down to subcontractors
The terms that decide when retained money comes back.
For estimators

Retainage Changes When You Get Paid on Every Bid

On a $2 million job with 10% retainage, $200,000 can sit with the owner for months after the crews have left. Before pricing, the bid team checks the retainage rate, the release point and whether the general contractor's terms match what it will hold from its subcontractors. On long jobs, some contractors add the cost of carrying that cash to their markup.

12-Month Job · Retainage HeldTraced
Month 3 billed to date$600,000
Month 3 retainage held$60,000
Month 6 retainage held$120,000
Month 9 retainage held$180,000
Month 12 retainage held$200,000
Released at completion$200,000
Illustrative example. Retainage builds up month by month and comes back at completion.
The Takeoff AI

These terms sit in the contract and general conditions, far from the drawings. The Takeoff AI reads the scope of work and technical specifications alongside the drawings, flags deviations between the three and returns the counted and priced scope, so the estimator can weigh the payment terms against a number already checked.

  • Scope counted and priced from the drawings, traced to the sheet
  • Deviations flagged across the scope of work, specifications and drawings
See Your Scope Counted and Priced
Why it matters in 2026

Longer Jobs Hold Your Cash for Longer

Retainage is held from the first pay application to the last, so the longer the job, the more cash sits with the owner. On large industrial and data center projects that run for years, a 10% hold can rival the profit on the job. On public projects, many states also set their own limits on retainage. Reading those terms before the number goes in is part of pricing the job.

“Retainage never shows up on the takeoff, but it shows up in your cash flow.”
Cash held back on a $2m job: month 4 $67,000, month 8 $133,000, month 12, before release $200,000CASH HELD BACK ON A $2M JOBMonth 4$67,000Month 8$133,000Month 12, before release$200,000
Retainage builds up every month the job runs.

Trusted by 200+ enterprises across EPC, Infrastructure, and Energy

American Steel Fabricators logothyssenkrupp logoToyo Engineering logoAllscope Services logoKalpataru logoGE logoSPG Dry Cooling logoPructon logoPerformance Energy Services logoNelpro Project Solutions logoCE Family logoConsolidated Fabrication and Constructors logoAmerican Steel Fabricators logothyssenkrupp logoToyo Engineering logoAllscope Services logoKalpataru logoGE logoSPG Dry Cooling logoPructon logoPerformance Energy Services logoNelpro Project Solutions logoCE Family logoConsolidated Fabrication and Constructors logo
American Steel Fabricators logothyssenkrupp logoToyo Engineering logoAllscope Services logoKalpataru logoGE logoSPG Dry Cooling logoPructon logoPerformance Energy Services logoNelpro Project Solutions logoCE Family logoConsolidated Fabrication and Constructors logoAmerican Steel Fabricators logothyssenkrupp logoToyo Engineering logoAllscope Services logoKalpataru logoGE logoSPG Dry Cooling logoPructon logoPerformance Energy Services logoNelpro Project Solutions logoCE Family logoConsolidated Fabrication and Constructors logo
Rated 5 out of 5 on G2
The Takeoff Handbook

Reference the Estimating Library

Practical takeoff references, charts and workflow guides, built for working estimators.

Before you ask

Retainage in Construction: How It Works on a Bid

Retainage is money held back from each progress payment until the project is finished and accepted. It is usually 5% to 10% of every payment and protects the owner if work is left incomplete or defective.