What Is Piping Fabrication?
Pipe fabrication, also called pipework fabrication, moves as much welding as possible off site and into a controlled shop. Welds made at bench height in a pipe fabrication shop are faster and more consistent than welds made in position on a pipe rack, so industrial pipe fabrication builds most of a system as spools and leaves only the tie-in welds for the field.
Pipe fabricators range from in-house shops at mechanical contractors to dedicated shops that fabricate for many contractors. Process piping fabrication for refineries and chemical plants follows ASME B31.3, which sets the welding, examination and testing rules. The pipe fabrication software entry covers the tools shops use to run this work.
What Is a Pipe Spool?
A spool piece, or piping spool, is a section of piping made in the shop from pipe, fittings and flanges, sized to fit on a truck and through the site. Pipe spool fabrication starts from the spool drawing, which shows one spool with its cut lengths, fittings, welds and weld numbers. The pipe spool entry covers spools in more detail, and the weld map entry covers how welds are numbered.
Spool Drawings and the Pipe Fabrication Process
A spool drawing, or pipe spool drawing, is cut from the isometric. It lists every piece, every cut length and every weld, so the shop can cut, fit and weld without going back to the isometric. Spool fabrication then follows the pipe fabrication process in the table above, with each spool tagged so it can be tracked to site.
How Shop Hours Are Estimated
Weld hours = shop welds × pipe size (in) × hours per diameter inch
Shop hours = weld hours + cut and bevel hours + fit-up and handling hours
Weld labor is priced in diameter inches because a large weld takes longer than a small one. Thick walls, alloy materials and heat treatment raise the hours per diameter inch, and the percentage of welds examined adds inspection cost.
Spool Fabrication Hours Calculator
Put in the welds, cuts and spools on a job to see the shop hours they take. The starting values are examples.
Total shop hours add weld hours, cut and bevel hours, and handling for each spool. Fit-up is included in the hours per diameter inch here; split it out if your shop tracks it separately.
Common Mistakes on a Fabrication Estimate
- Pricing shop and field welds at one rate
- Missing the cuts and bevels on every pipe end
- Leaving out heat treatment where the specification calls for it
- Using one examination percentage for every class
- Forgetting handling, tagging and shipping on large spool counts
How The Takeoff AI Handles Piping Fabrication
The Takeoff AI estimates the P&ID (piping and instrumentation diagram) drawings, isometric drawings, line lists and the specification, and takes off the piping end to end. It counts every spool, pipe length, fitting, flange, valve, bolt, gasket, support and weld, splits shop and field welds, works out diameter inches, and prices the material takeoff (MTO) and labor takeoff (LTO) into a priced bill of materials (BOM) at your own rates.
Its nesting fits pipe cuts onto stock lengths, and it builds a 3D model from the 2D drawings. Every quantity is highlighted on the sheet it came from, and it is trained on more than 1 million drawing sets and runs at 95% accuracy. 113 estimators say The Takeoff AI is the best piping estimating software they have used, and it helps them estimate projects in 3 to 4 hours that once took 40 to 50 hours. See it on the piping page.