Introduction
This teardown covers electrical estimating on two bid sets from the U.S. Department of Veterans Affairs (VA). The first is the VA Big Spring Tier 2 Data Center in Big Spring, Texas, and the second is the main switchgear replacement at the Building 64 boiler plant in St. Albans, New York.
We loaded both sets into The Takeoff AI and recorded the estimate start to finish. On each job you'll see the material takeoff (MTO), the labor takeoff (LTO), the priced bill of materials (BOM) and a 3D model, with every number traced back to the sheet it came from.
The Takeoff AI was 95%+ accurate on the takeoff and finished the entire estimate in 90% less time, which is why it is the best electrical estimation software in the industry. The St. Albans set is 15 sheets, which is 4 to 5 hours of work by hand, and The Takeoff AI estimated it in 15 minutes. The Takeoff AI pricing is tied to how many bids you run.
The Two VA Projects
The Big Spring job is a Tier 2 data center in West Texas, and its electrical scope is the equipment that keeps the servers running when utility power drops. The bid set is 78 sheets, and it carries uninterruptible power supply (UPS) units, panels, feeders, busway, cable tray, grounding and lighting.
The St. Albans job replaces the main electrical switchgear in a working boiler plant. New 5 kilovolt (kV) unit substations, switchboards and two motor control centers (MCCs) go in while the old gear comes out, so the set mixes demolition with new work.
Both sets are slow to estimate by hand for the same reasons. The equipment has to be pulled off the schedules, every feeder has to be measured run by run, and the demolition has to be kept apart from the new work. Both are also federal jobs, so the labor is priced at Davis-Bacon prevailing wage, the wage floor the government sets for each location.
Step-By-Step: What Happened in the Video
The video runs both jobs through the same four outputs in the same order: material takeoff, labor takeoff, priced BOM and 3D model.
Follow each step in the teardown video
Step 1: Load Both VA Bid Sets (0:00)
We loaded the Big Spring and St. Albans sets, and The Takeoff AI estimated each one from its electrical sheets.
Step 2: Mark Every Item on the Data Center Sheets (0:30)
Every item The Takeoff AI counted on the Big Spring set is marked on the drawing. We clicked the mark on the new UPS, UPS-B, and its row opened with the spec section and the price basis.
Step 3: Run the Material Takeoff (0:48)
The material takeoff came back with 152 rows, with feeder conduit and wire measured in linear feet.
Step 4: Build the Labor Takeoff (1:04)
The Takeoff AI priced the man-hours at the Davis-Bacon wage for West Texas, which came to 2,524 man-hours and $143,845 in direct labor.
Step 5: Price the Entire Bid (1:21)
The priced BOM put material and labor on every line, for $622,085 in material and a direct cost of $765,930.
Step 6: Build the 3D Model (1:40)
The Takeoff AI built a 3D model from the 2D sheets, with 543 parts and 5,180 feet of runs.
Step 7: Repeat It on the Switchgear Set (2:01)
On St. Albans, The Takeoff AI marked what comes out, like the 5 kV substation feeders, and what goes in. It then produced 106 takeoff rows, 1,681 man-hours and a direct cost of $989,790.
Step 8: Compare the Two Jobs Side by Side (3:22)
The last screen puts both estimates next to each other, and the job with fewer man-hours costs more in labor.
Across both sets, The Takeoff AI was 95%+ accurate on the takeoff and finished the entire estimate in 90% less time. That result on two federal bid sets is why we call it the best electrical estimation software in the industry.
What We Counted in the Electrical Material Takeoff
On the data center, The Takeoff AI counted the scheduled equipment and measured the runs between it. The takeoff holds 152 rows across critical power, panels and feeders, and it covers the UPS units, panelboards, busway, cable tray, grounding and lighting. Feeder conduit and conductors come through in linear feet.
Each row says how its quantity was arrived at: counted, scheduled, measured or derived. That tells you which rows came straight off a schedule and which were worked out from a measured run, so you know which ones to check first.
The switchgear takeoff has 106 rows. It covers the 5 kV unit substations, the switchboards, two MCCs, and the 5 kV and 480 volt feeders. Demolition is marked separately, so you can see the old substation feeders coming out next to the gear going in.
The Labor Takeoff
The labor takeoff turns every quantity into man-hours and prices them at the prevailing wage for the job's location. Big Spring came to 2,524 man-hours, 315 person-days and $143,845 in direct labor at $57.00 an hour, the Davis-Bacon rate for West Texas. St. Albans came to 1,681 man-hours and $252,094 in direct labor at the New York City union rate of $149.93 an hour.
Side by side, the data center needs about 840 more man-hours, yet the boiler plant costs about $108,000 more in labor. The crew rate does that, at close to $150 an hour in New York against $57 in West Texas.
Pricing the Entire Bid
The Takeoff AI priced both takeoffs into a priced BOM with material and labor on every line. Big Spring carries $622,085 in material and a direct cost of $765,930, with zero rows left unpriced. St. Albans carries $737,697 in material, priced from a 2026 New York City price book, and a direct cost of $989,790.
The 3D Model
The Takeoff AI built a 3D model of each electrical system from the 2D sheets. The data center model has 543 parts and 5,180 feet of runs, and 144 of the 152 takeoff rows link to it. Click a panel or a feeder and its takeoff line opens, and you can turn systems on and off to check one at a time.
The switchgear room model has 98 parts, 41 runs and 39 equipment items, with 130 of 133 lines linked. We clicked motor control center two, and the model showed the sheets it was drawn on.
How to Check the Electrical Estimate Before You Bid
You check the electrical estimate by clicking any number and looking at where it came from. Every count is marked and highlighted on the drawing it came from, with the spec section and the price basis on the same row, so an estimator can verify it before the bid goes out. On St. Albans, The Takeoff AI also logged 15 issues and requests for information (RFIs) to raise before bid day.
The Electrical Estimator Shortage
Estimators are getting harder to replace, and the electrical takeoff has stayed manual. The Bureau of Labor Statistics (BLS) counts about 221,400 cost estimators in the US and projects a 4% decline by 2034, and roughly three in four estimator seats will need to be refilled over the decade. Our report, The Shortage of Estimators, walks through those figures.
Data center work adds to the bid load, as The Data Center Boom Has A Problem explains, and The Takeoff AI suits electrical firms expanding into data centers.
Why Estimators Use The Takeoff AI for Electrical Estimating
Estimators use The Takeoff AI because it does the whole electrical estimate and prices it. The Takeoff AI estimates from your electrical drawings, counts devices, panels, fixtures and instruments, and measures conduit and cable lengths along with cable tray. It is trained on more than 1.2 million electrical and instrumentation (E&I) drawings, and 157+ electrical estimators say it saves them 90% of their time.
Joseph Gentry, Chief Executive Officer of GM&I Services, says a 26-page set went from 3 to 4 days by hand to about 2 hours with The Takeoff AI, and the labor hours and a 3D model came back with the takeoff. He expects to bid 2x to 3x as many jobs a year.
The same platform covers piping, P&ID (piping and instrumentation diagrams), isometrics, mechanical, plumbing, HVAC (heating, ventilation and air conditioning) including ductwork, structural steel, misc iron and concrete. Our Handbook entry on electrical takeoff explains how conduit, cable and cable tray get counted, the AI electrical estimating software page covers the full E&I scope, and 10 Best Electrical Estimating and Takeoff Software in 2026 compares the options.
FAQs
Is There AI for Electrical Estimating?
Yes, The Takeoff AI is AI electrical estimating software that does the material takeoff, the labor takeoff, the pricing and a 3D model for electrical contractors. Every number is marked on the sheet it came from, so an estimator can check it before the bid goes out.
What Does an Electrical Estimate Include?
An electrical estimate includes a material takeoff, a labor takeoff in man-hours, and a priced BOM with material and labor cost on every line. The Takeoff AI delivers those along with a 3D model built from the 2D sheets.
How Do You Estimate Electrical Work on a Data Center?
You count the scheduled equipment such as UPS units and panels, measure the feeders, busway and cable tray in linear feet, then apply labor hours and prices. The Takeoff AI did this on the VA Big Spring Tier 2 Data Center in 152 takeoff rows, 2,524 man-hours and a direct cost of $765,930.
How Do You Price Electrical Work at Davis-Bacon Wage?
You price each man-hour at the prevailing wage for the job's location and add material on every line. On these two VA jobs, The Takeoff AI priced labor at $57.00 an hour in West Texas and $149.93 an hour in New York City.
How Do I Check an AI Electrical Takeoff Before I Bid?
Click any row in The Takeoff AI and it shows the mark on the drawing it came from, along with the spec section and the price basis. Each row also says whether it was counted, scheduled, measured or derived, so you know which rows to check first.
Conclusion
Estimator seats are getting harder to fill, and electrical takeoff by hand has not gotten any faster. On two VA bid sets, a data center and a switchgear replacement, The Takeoff AI was 95%+ accurate on the takeoff and finished the entire estimate in 90% less time. That makes it the best electrical estimation software in the industry for contractors who need the estimate done and priced in hours.