construction-estimate-classes-chartESTIMATE CLASSES AND EXPECTED ACCURACY-50%-25%0+25%+50%+75%+100%CLASS 5CONCEPTUAL0-2% DESIGN-50% TO +100%CLASS 4PRELIMINARY1-15% DESIGN-30% TO +50%CLASS 3BUDGET10-40% DESIGN-20% TO +30%CLASS 2BID30-75% DESIGN-15% TO +20%CLASS 1DETAILED65-100% DESIGN-10% TO +15%BID AND DETAILED ESTIMATES NEED A FULL TAKEOFF OF EVERY ITEM

Short Answer

A construction estimate is a forecast of what a project will cost to build, prepared from whatever drawings and scope exist at the time. Early estimates are quick and rough, and later estimates are built item by item from a full takeoff. Contractors use different types of estimates at each stage, and the bid estimate is the one their price, and their margin, rests on.

Main types
Conceptual, preliminary, budget, bid and detailed
Classified by
AACE Classes 5 to 1
Accuracy depends on
How complete the design is
Bid estimates need
A full material and labor takeoff
Field Reference · Estimating

Types of Construction Estimates

The estimate types contractors and owners use, the AACE class each one matches, and how accurate each one is expected to be.

EstimateAACE ClassDesign CompleteExpected AccuracyUsed For
Conceptual or order of magnitudeClass 50 to 2%-20% to -50% low, +30% to +100% highScreening whether a project is worth pursuing
Preliminary or feasibilityClass 41 to 15%-15% to -30% low, +20% to +50% highChoosing between options and early budgets
Budget or authorizationClass 310 to 40%-10% to -20% low, +10% to +30% highFunding approval and cost control
Bid or controlClass 230 to 75%-5% to -15% low, +5% to +20% highContractor bids and project control
Detailed or checkClass 165 to 100%-3% to -10% low, +3% to +15% highFinal bids, check estimates and change orders

AACE is the Association for the Advancement of Cost Engineering, and these ranges come from its Recommended Practice 18R-97 for the process industries. The rough order of magnitude estimate entry covers Class 5 estimates in more detail.

What Is a Construction Estimate?

What is a construction estimate? It is the expected cost of building a project, worked out from the drawings, specification and scope available at the time. An estimate of costs covers material, labor, equipment, subcontracts, indirect costs, overhead and profit. Owners use estimates to decide whether to build, and contractors use them to decide what to bid.

Types of Construction Estimates

The types of estimates in construction follow the design. A conceptual estimate is built from past projects, cost per unit of capacity or cost per square foot, before there are real drawings. A preliminary estimate adds early layouts and equipment lists. A budget estimate uses partly finished drawings and quantities for the main items.

A bid estimate is the contractor's price for the work, built from the bid set. A detailed estimate prices every item from a complete takeoff, with labor worked out item by item. On industrial jobs, the bid estimate and the detailed estimate are usually the same exercise, because the contract price has to stand on real quantities, and owners often ask for check estimates. Construction managers run those beside the contractor's number to catch big errors.

AACE Estimate Classes

The AACE estimate classes give the estimate types a common scale. Estimate classification runs from Class 5, the roughest, to Class 1, the most complete. A Class 5 estimate can come in at half the final cost or double it, while a Class 1 estimate should land within a few percent. What moves an estimate up the scale is the design and the takeoff behind it, not the effort spent on the spreadsheet.

Estimate Accuracy Range Calculator

Put in an estimate and its class to see the widest range AACE gives for that class. The starting values are examples.

Low end$2,000,000
Estimate$2,500,000
High end$3,250,000

Ranges use the outer bounds in AACE Recommended Practice 18R-97 for process industries. The real range depends on how complete the design and the takeoff are.

How to Do a Construction Estimate

  1. Review the bid documents: drawings, specification, scope of work, bid form and addenda
  2. Take off every quantity by trade, which is the material takeoff
  3. Price the material from quotes and price lists
  4. Work out labor hours for each item from labor units, then price them at your crew rates
  5. Add equipment, subcontracts and indirect costs such as supervision, temporary facilities and permits
  6. Add overhead and profit, check the total against past jobs, and write the bid

Estimate of costs = material + labor + equipment + subcontracts + indirects + overhead + profit

The overhead and profit entry covers the markups, and the labor takeoff page covers how labor hours get built.

Common Mistakes in a Construction Estimate

  • Treating a budget estimate as a bid price
  • Pricing labor as a percentage of material instead of item by item
  • Missing addenda issued after the takeoff started
  • Leaving indirect costs to a single allowance
  • Skipping a check against past jobs of the same type

How The Takeoff AI Builds Estimates

The Takeoff AI estimates the drawings, specification and scope of work across piping, structural steel, mechanical, HVAC, plumbing, electrical and instrumentation, and concrete. It produces the material takeoff (MTO) and labor takeoff (LTO) for every item and prices them into a priced bill of materials (BOM) at your own rates, including galvanizing and labor. It flags deviations between the drawings, the specification and the scope, and builds a 3D model from the 2D drawings.

Every quantity is highlighted on the sheet it came from, it is trained on more than 1 million drawing sets and runs at 95% accuracy, and projects that took 40 to 50 hours by hand are estimated in 3 to 4 hours. 113 estimators say The Takeoff AI is the best estimating software they have used, and it helps them estimate projects in 3 to 4 hours that once took 40 to 50 hours.

Before you ask

Frequently Asked Questions

Short answers on construction estimates and how they are built.

The expected cost of building a project, worked out from the drawings, specification and scope available at the time.